Tower Crane Dismantling Method Statement ((top)) -
[Insert Capacity, e.g., 200-ton Mobile Crane] with sufficient boom length.
This cycle repeats: lower, unbolt one mast section (typically 2.5–3m tall), slide it down via the climbing frame, and pass it to the ground crew. tower crane dismantling method statement
The following method statement outlines the procedures for the safe dismantling of a tower crane. The crane in question is a [insert crane model, e.g., Liebherr 630 EC], with a height of [insert height, e.g., 80 meters] and a lifting capacity of [insert lifting capacity, e.g., 10 tons]. The crane is located at [insert location, e.g., a construction site in downtown city]. The dismantling work will be carried out by a team of experienced personnel from [insert company name, e.g., Crane Solutions Ltd.]. [Insert Capacity, e
| Condition | Action | |-----------|--------| | Wind speed > 20 mph (9 m/s) | Stop all lifts above 50ft height. | | Wind speed > 25 mph (11 m/s) | – secure partial load. | | Rain / fog (visibility < 50m) | Stop work. | | Lightning within 10 miles | Stop work, evacuate crane area. | | Night work | Only permitted with full lighting (500 lux minimum). | The crane in question is a [insert crane model, e
Remove the specified number of counterweight blocks as per the manufacturer's manual to maintain balance.